- Third Party to conduct the SIS*
- Vicinity map of the Project
- Single Line Diagram of the proposed connection scheme/s indicating the parameters of the connection facilities such as line structure, conductor type and distance, and transformer capacities
- Generator modeling parameters
- Transmission Service Application Form (TSAF)
- Agreement on Offer of Service
- Tripartite Confidentiality Agreement
III - HOW MUCH TO PAY?
≥50 MW = Php1million
60% down and 40% before SIS delivery
*If SIS is conducted by a Third Party, NGCP charges Data fee and Review Fee.
Please see concerned officers for rates.
I - HOW TO APPLY?
- Download and accomplish Transmission Service application forms
- File the application and submit all necessary documents (refer to Section II below)
- Pay the required fees (see Section III below)
- Visit NGCP website or call for more information and guidance
- Obtain the Certificate
II - WHAT ARE THE REQUIREMENTS?
- Letterof Application for Transmission Service
- ERC Load Approval
- DOE Accreditation (Generator)
- System Impact Study
- Offer of Service for Facilities Study
- Connection Agreement
- Submission of Statement of Readiness to Connect
- Issuance of Certificate of Technical Requirements
- District Office Clearance
- Metering Services Group (MSG) Clearance
- Maintenance and Testing Division (MTD) Clearance
- System Operator (SO) Clearance (if applicable)
- Open Access Transmission Service (OATS) Services
- Standard Planning Data
- Detailed Planning Data (for Generator Customers)
- Electrical Drawings
- Connection Point Drawings
- Asset Boundary
- Protection Arrangement and Settings
- Metering Requirements
- Notices
- Provisional Maintenance Schedule
- Testing and Commissioning (new delivery Point)
- Load Shedding
- Contingency Actions
- Critical Events List
- Statement of Readiness to Connect (new delivery Point)
III - HOW MUCH TO PAY?
- Customer Bulletins for the updates on Schedule of Rates/Fees